New dates for Concord lane closures


REVISED RELEASE - THE DATES FOR THIS PROJECT HAVE BEEN MOVED UP DUE TO THE WEATHER. SEE THE NEW DATES BELOW. THANK YOU FOR YOUR PATIENCE

Upcoming pavement repair work in Concord on Walters Way and at the Monument Boulevard/ Detroit Avenue intersection will require lane reductions on Walters Way and closure of the Monument Boulevard/ Detroit Avenue intersection (see details below). To minimize disruption, the intersection closure will be conducted at night and a detour route will be posted. Please drive safely if you're in the area.

(1) Monument/Detroit intersection
The intersection will be closed during two separate nights as follows, for grinding and paving operations. Follow detour signs.
Date: Wednesday, October 26, 2016
Start Time: 8:00 p.m. - Full intersection closure with detour.
End Time: 5:00 a.m. on Thursday, October 27, 2016

Date: Tuesday, November 1, 2016
Start Time: 8:30 p.m. - Full intersection closure with detour.
End Time: 5:00 a.m. on Wednesday, November 2, 2016


(2) Walters Way
Grinding and leveling course paving operations
Date: Monday, October 31, 2016
Start Time: 7:00 am - Traffic lanes will be shifted, maintaining a minimum of 10’ traveled lane in each direction.
Lane Closure: 9:00 am - Lanes will be closed using one-way flagged traffic.
End Time: 3:30 pm

Surface Course Paving Operations
Date: Tuesday, November 1, 2016
Start Time: +/- 12:00 noon- Lanes will be closed using one-way flagged traffic.
End Time: 7:00 pm

For more information, contact Senior Civil Engineer Mario Camorongan, (925) 671-3021.



 